Msheireb Metro Station, Qatar

Projekti andmed

Asukoht: Qatar, Katar

Subway station in the heart of Doha as lynchpin of the currently under construction state-of-the-art metro system in the capital of Qatar.

Major interchange featuring a toal of four main levels at depths of up to 40 m.

Tellija poolsed ootused

  • High demands placed on the execution of the construction due to the inner-city location of the construction site and the imposing 200 m long and 180 m wide structural dimensions.
  • Complex structural geometry as well as massive reinforced concrete components with up to 3 m thick slabs and wall thicknesses up to 2 m.

Klient

SOQ Joint Venture; Samsung C&T, OHL, QBC

Lisaväärtus

  • Fast construction progress due to the individually adapted system concept and continuous on-site support.
  • Cost-effective construction execution through just-in-time provision of materials.
  • Realization of the ambitious infrastructure project within the tight construction schedule.
Portrait of Carlos Allepuz, Construction Manager, SOQ Joint Venture; Samsung C&T, OHL, QBC
Carlos Allepuz
Construction Manager

PERI engineers have given us full round-the-clock technical support and reliable after sales service from day one. This close cooperation has enabled SOQ JV to use PERI cutting-edge solutions to build this very important station efficiently, safely and successfully.

PERI lahendus

  • Project-specific implementation concept on the basis of system equipment.
  • Fast provision of materials within a very short period of time: 10,000 m² wall and column formwork as well as 150,000 m³ shoring.
  • Wall formwork solution on the basis of the VARIO Girder Wall Formwork System and supplemented, if required, with SB Brace Frames and CB Climbing Platforms.
  • Customized shoring concept with PD 8 Shoring Towers, MULTIPROP Aluminium Slab Props and the PERI UP Flex Shoring System.