Internal view of resevoir walls. Neat high concrete finish of walls. Personnel show shear height of resevoir walls

Projektide ülevaade

Koos klientidega loome suurepäraseid asju. Olgu need tellingud, pilvelõhkujad, sillad või tunnelid, näitame teile millised projektid oleme koos klientidega realiseerinud.

Kõik projektid

Maakri kvartal
Kõige paindlikum, mitmekülgsem ja raha säästvam laeraketise süsteem Eestis. Avatud hoone fassaadi korral, kui ei esine kandvaid välisseinu, kasutatakse laeraketise lahendusena võimalikult palju lavaraketist. Lavaraketis on kasutatav kiireteks valutsükliteks kogu hoone ulatuses.
9m kõrgune ja 1m paksune sein ühe valuga.
The use of efficient formwork systems for the walls and slabs ensured that the very tight completion deadline for the building shell could be met.
For the reconstruction of the Berlin City Palace, PERI supplied cost-effective formwork and scaffolding solutions from one source. Apart from short shuttering and moving times, the on-site support provided by the PERI engineers in particular ensured that the tight construction schedule could be maintained.
Combination of two climbing systems used as ACS required to raise all platforms simultaneously. ACS system pre-fabricated at the Rugby Depot due to site space constrictions
Concrete House, Sussex
The complex construction project with highest quality requirements demanded an experienced construction site team as well as on-site support through PERI engineers.
With the help of the customized PERI formwork and scaffolding solution, a new campus complex is being realized in Lima – with high architectural requirements and a tight construction schedule.
Meeting formwork demands on Hinkley Point C
For these cores on the V&A Stratford project, we provided ‘up and over’ access using our PERI UP Flex scaffold so operatives could gain access from one side of the VARIO formwork shutter to the other. This was crucial as the final floor levels followed up behind the core and were not yet in place.
With a height of 220 m, the new office tower of the "Warsaw Spire" building ensemble will be the tallest office building in Warsaw after completion. Two office buildings flank the tower, each 55 m high.
This extraordinary structure is characterized by twisting reinforced concrete walls which reach heights of up to 14 m.
PERI supplied a project-specific formwork and scaffolding solution and supported with comprehensive engineering services for the construction of the 108-m-high complex dam on the River Tua in Portugal.
The outside of the building resembles a medieval fortress. The facade is comprised of window openings as well as pre-determined regular tie points and horizontal pilaster strips.
RCS climbing protection panel ensures workers' safety and completely encloses the construction area
Working platforms and integrated access provides safety at height for construction workers using the PERI UP Rosett Flex Modular Scaffolding System
With formwork and scaffolding systems perfectly matched each structural component, the concrete frame could be completely finished in only 9 months.
The A52 Clifton Bridge, a major National Highways upgrade project in Nottingham, is a complex structure, which required repairs inside and underneath the bridge to strengthen the concrete.
alrimal site Riyadh .
Increased efficiency with optimized team capacity
&lt;b&gt;Kõige paindlikum, mitmekülgsem ja raha säästvam laeraketise süsteem Eestis&lt;/b&gt;<br/><br/>Avatud hoone fassaadi korral, kui ei esine kandvaid välisseinu, kasutatakse laeraketise lahendusena võimalikult palju lavaraketist.<br/>
The Potsdamer Platz is a city of the future with office and residential buildings, schools, theatres, hotels and shopping centres in the heart of Berlin.
The three spectacular buildings of the new Zollhof complex in Dusseldorf during different stages of construction.
Ultramodernne ja tõeliselt urbanistlik Ülemiste City ärilinnak areneb suurel kiirusel. 13-korruselisele Öpiku esimesele majale on kerkimas kõrvale ka teine, moodustades seni suurima büroohoonete kompleksi Eestis.
Sepapaja 1 büroohoone
With the help of the PERI UP Rosett modular scaffold system, 24-metre high shoring was erected at the main entrance of the temple. Even at large heights, up to 40 kN per leg could be safely and reliably transferred.
Spectacular view of the City of London from One Tower Bridge
Delivering a high-grade architectural finish for a world-changing university.
One of the most significant infrastructure projects ever undertaken in the UK, London’s Crossrail is a high-frequency, high-capacity service enabling faster travel across the capital.
The 258 m long and 50 m high arched bridge crosses the Opamo Valley in the Bohemian Forest.
VARIOKIT in place in the Station&#039;s tunnel allowing construction work to be undertaken without impeding the safety of workers
The Smithland hydroelectric power plant is equipped with 3 turbines; due to the extremely tight construction schedule, all three tubes with their constantly changing cross-sections are being realized at the same time.
With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method. For the construction of the motorway bridge near Tarnow, the construction crew achieved a 4 to 5-day cycle thanks to the easy to use, mechanical solution. At the same time, the high requirements concerning the very small tolerances for the variable bridge cross-sections could be fulfilled.
Massive, 28 cm thick reinforced concrete balconies cantilever outwards for 3.35 m in an irregular fashion on all four sides of the building.
The temporary works provided support to the 14.50m 2-floor element and pvodided a matrix of steel-deck working platforms enabling safe access and close monitoring during massive concrete pours
The Mersey Gateway is a cable-stayed bridge stretching over 2,000 m from Runcorn to Widnes
Bold designs and extraordinary architectural concrete fulfilled. In addition, the utmost accuracy was required for the subsequent glazing work
The Werrington Grade Separation scheme will make way for a new diveunder railway line.
Efficient formwork and falsework for one of Scotland’s busiest roads.
Replacing the membrane was carried out during ongoing daily airport operations. Maximum safety was ensured through a large-area protective roof construction installed at the height of the forum area in addition to the safety netting underneath the scaffolded roof sections.
For the renovation of an arched bridge built in 1940, a scaffold construction on the basis of PERI UP modular scaffolding was erected.
The 33 m high and 60 m long sculpture ensemble, featuring Pegasus and a dragon, was realised in a larger than life size. With the help of the PERI UP solution, more than 1,000 bronze castings could be assembled and welded on site.
The complex includes a 1,800-seat opera house, a concert hall for 1,100 music lovers as well as a theatre for audiences up to 2,000.
PERI UP Rosett formed the falsework construction and was erected according to the type test. The tight construction schedule required support along the entire length of 75 m.
With 77 t of PERI UP Rosett materials, the building´s design could be accurately realized as a three-dimensional spatial load-bearing structure.
Steel reinforcement ties the core together
Thanks to the detailed planning provided by PERI engineers and high flexibility of the PERI balanced cantilever equipment, the superstructure of the cable stay bridge could be completed according to the schedule.
More than 12 months after starting the development work on the Panama Canal, the dimensions and the massive structural elements are clearly visible.
Zahid Business Park
The museum shape symbolizes a traditional village hut, which gradually crumbles into dust. Numerous offsets and inclined surfaces characterize the complex structure. PERI engineers developed a customized formwork concept in order to carry out the project with a minimum quantity of special formwork.
With a height of 415 m, the Trump International Hotel and Tower on the Chicago River is a very impressive skyscraper.
The southern entrance area was constructed using the cut-and-cover method for a length of around 1.5 km. With the two PERI formwork carriages, the walls and slabs of the two separate tunnels could be cost-effectively concreted in one pour.
The almost 100 m long Libeskind-designed structure features a 30-metre high wedge tip made of glass and steel.
The PERI solution served as both shoring and an assembly platform on which the enormous steel trusses of the roof construction were set down, assembled and moved into position.
A total of 8,500 m² of exhibition space is now available under the three domes.
Apart from the two pylons, a total of nine double piers are being constructed on both sides of the ravine which are braced by means of massive cross beams.
For the 1,083 m long Trmice motorway bridge near Aussig in the Czech Republic, 59 piers were cost-effectively formed using PERI formwork.
The large spans in the middle bridge sections were concreted by means of the balanced cantilever method.
Up to 30 m high VARIOKIT VST heavy-duty shoring towers served as falsework for the construction of the bridge edge sections. Each leg carried a load of around 600 kN.
In the complex area with an extremely tight outer radius, the concentrated loads of the radially-arranged cantilever brackets are transferred into the available bridge piers by means of pressure supports.
A VARIOKIT cantilevered parapet carriage serves for constructing the external cantilevered parapets. The horizontal loads are transferred via friction, anchoring is not required.
In the area of the double piers, 14 complete ACS self-climbing units with telescopic working platforms were used.
The drum formwork was integrated with heavy-duty trusses comprising RCS rail frames and heavy-duty rollers to facilitate movement.
The Tideway project will redirect sewage overspill from the most polluting overflow points via purpose-built shafts along the River Thames.
In 25 m long concreting steps and four cycle sequences, the tunnel bottom plate, two wall sections respectively and then the slab could be concreted one after the other.
In the US state of Louisiana, three enormous liquid gas tanks were simultaneously realized using PERI know-how. Each of the structures has an 80 m diameter and a wall height of 44 m.
For the power plant construction in Eemshaven, the industrial scaffold system PERI UP has clearly demonstrated its flexibility and adaptability.
Easy to mount and move manually
A total of 9 circular piers with 3.60 m diameters and 40 cm wall thicknesses will subsequently carry a steel platform for the condenser.
The LGS Weather Protection Roof on the basis of the PERI UP Scaffolding System made the roof renovation independent of the weather. The 90 m long protection roof consisted of 3 m wide and nearly 30 m long LGS segments.
Cost-effective PERI climbing concept: with a complete platform level and halved on-site wall formwork requirements, fast and continuous working operations were achieved.
With the selected PERI formwork and scaffolding systems, the construction team was able to cost-effectively fulfil all requirements in spite of the tight construction schedule. The solutions developed by PERI engineers and the local site management, along with support provided by PERI specialists, contributed to efficient and problem-free construction.
The variable VARIO girder wall formwork, together with SKS climbing scaffold, formed large area transportable units.
For extending the cement plant, engineers from PERI Ukraine designed a comprehensive and sophisticated formwork and scaffolding solution.
The two-storey supporting structure, with a height of 25 metres, accommodates the sorption installation for the flue gas desulphurisation.
Each of the two towers has three reinforced concrete cores which were constructed with help of two PERI ACS self-climbing variants.
A complete solution consisting of formwork, scaffolding and related services has guaranteed safety at all heights and rapid progress during the construction of JKG Tower complex.
The PERI CPP climbing protection panel reliably encloses the upper floors under construction.
The American Las Vegas Sands Corporation is the owner of the complex the highly visible hotel towers.
The RCS climbing protection panel complete encloses the upper floors under construction and provides protection against wind and weather - and increases productivity.
The ISET Tower in Yekaterinburg is characterized by its external shape. PERI planned a comprehensive, crane-independent concept of the climbing formwork required on the elevator shafts and core walls, as well as the climbing protection panel on the building´s outer edges.
Already during the construction phase, the Al Hamra Tower stood out through its timeless elegance which was achieved by turning the external facade by 130 degrees.
Inclined and crane-independently climbed RCS protection panel units provide here a very high level of safety.
The cylindrical core and facade walls of this 142 m high office building were constructed with PERI ACS self-climbing technology.
For the very wide range of requirements, PERI provided the most cost-effective solution with the ACS self-climbing formwork.
Habtoor Residences project using PERI ACS Automatic Climbing System
The perfectly adapted shoring and working scaffold optimally supplemented the cost-effective formwork solution.
For the construction of the Hotel Meliá in the La Défense office district, PERI developed a comprehensive climbing formwork solution. This serves not only as an enclosure, which ensures the safety of the construction teams at all times, but also it supports the precast parapets during erection.
One climbing system – two climbing methods: with protection provided by the RCS climbing protection panel, the two twisting Absolute World towers rose steadily upwards in regular weekly cycles.
The PERI UP scaffolding extended upwards on the outside keeping pace with the construction progress.
A standardized construction kit system as well as the planning and delivery of formwork and scaffolding from a single source makes the PERI project solution very cost-effective.
Not far from Warsaw‘s city centre, the new headquarters building of the automotive group together with a Mercedes-Benz dealership containing showrooms and a service centre has been realized.
For the construction of the new ADAC headquarters, PERI supported the Züblin construction team with efficient formwork and scaffolding solutions as well as competent service.
Strong and reliable support up to 14m high with PERI UP shoring system
The challenging building form called for flexibly adaptable formwork and scaffolding systems.
The new 6-star hotel complex was constructed around two buildings dating from the colonial times. With SKYDECK, the construction of the reinforced concrete slabs could be carried out efficiently and safely.
Built to coincide with “Porto 2001 – European Culture Capital”, the concert hall is pictured here after structural work had been completed.
The museum shape symbolizes a traditional village hut, which gradually crumbles into dust. Numerous offsets and inclined surfaces characterize the complex structure. PERI engineers developed a customized formwork concept in order to carry out the project with a minimum quantity of special formwork.
With an X-shaped floor plan, the architectural concept of this building created a new highlight in the urban development of the city of Hradec Králové. Originally, all external surfaces should have received an orange-painted facade. This concept was completely rejected due to the high-quality concrete surface finish.
A huge birdcage scaffold on the basis of PERI UP Rosett provided safe access ways and working areas for subsequent site activities up to a height of nearly 80 m.
For realising the extraordinary museum on time and within budget, PERI planned, produced and delivered over 3,500 customised special formwork elements.
The execution of this very impressive project required unique engineering and assembly implementation on the construction site.
The tent-like roof construction reached a height of 77 m. For the up to 32 m high PERI UP Rosett shoring towers, adapting to the complex roof geometry was carried out using system components from the VARIOKIT engineering construction kit.
PERI UP scaffolding on the longitudinal sides of the building was designed according to the expected loads and carried the construction loads.
Only when seen from an aerial perspective is the scale of the construction site really apparent: the area is the size of around 2,000 football pitches.
The Midfield Terminal Complex is the ultimate in construction sites: in order to maintain the tight construction schedule, PERI planned and delivered the formwork and scaffolding systems, and has provided yet another convincing performance through the competent engineering service and provision of huge quantities of materials at short notice.
The 600 m long, new satellite terminal at Munich airport is located in the centre of the airfield and encloses the apron tower and incorporates the existing baggage sorting centre. Construction is taking place during normal airport operations and presents an enormous challenge to all those involved in the project.
Work could be safely carried out on the spacious and geometrically adapted working platforms of the PERI UP Rosett scaffold which was erected up to the head of the statue.
The cantilevered working platform as seen from the visitors platform.
Accelerated refurbishment project: the customized project solution was based on two compatible PERI modular construction systems – VARIOKIT and PERI UP.
A huge birdcage scaffold on the basis of PERI UP Rosett provided safe access ways and working areas for subsequent site activities up to a height of nearly 80 m.
The Link, City Road
The pre-stressed hollow box superstructure was formed with VARIO GT 24 wall formwork and MULTIFLEX slab formwork.
The 2.00 m wide shoring scaffold sections are connected longitudinally by means of heavy-duty spindles and push-pull props to form shoring towers.

Kas olete huvitatud, kuidas saab PERI teie järgmist projekti toetada?